NEW QUESTION # 18
When doing a new implementation on premise or private cloud, which system is recommended to demonstrate standard functionality in the Explore phase?
- A. Sandbox
- B. Development
- C. Trial
- D. Starter
Answer: A
Explanation:
A Sandbox system is recommended in the Explore phase to demonstrate standard SAP functionality and conduct initial testing. This environment allows for configuration and testing without affecting the live environment, helping the project team understand standard capabilities.
NEW QUESTION # 19
Your customer is using a non-SAP ERP system and decides to deploy SAP S/4HANA. Which of the following options are available to your customer? Note: There are 3 correct answers to this question.
- A. System Conversion SAP S/4HANA
- B. New Implementation SAP S/4HANA Cloud, public edition
- C. System Conversion SAP S/4HANA Cloud, private edition
- D. New Implementation SAP S/4HANA
- E. New Implementation SAP S/4HANA Cloud, private edition
Answer: B,D,E
Explanation:
For customers migrating from a non-SAP ERP system, New Implementation paths, such as SAP S/4HANA Cloud (both public and private editions) or SAP S/4HANA on-premise, are viable options. System Conversion is not applicable as it is only for transitioning from an existing SAP ERP system.
NEW QUESTION # 20
Which of the following are capabilities of SAP Landscape Transformation Tool used in Selective Data Transition scenarios? Note: There are 3 correct answers to this question.
- A. Migration of selected applications
- B. Full set of historical transactional data
- C. Configuration of open backlog items
- D. Consolidation of systems
- E. Migration of business units
Answer: A,D,E
Explanation:
The SAP Landscape Transformation Tool enables selective migration by allowing the migration of specific applications and business units, as well as the consolidation of systems. It provides flexibility in data transition for selective data migration scenarios.
NEW QUESTION # 21
What is the difference between the System Conversion and New Implementation transition paths to SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Data is converted in System Conversion and migrated in New Implementation of SAP S/4HANA in the Realize phase.
- B. Data is migrated in System Conversion and converted in New Implementation of SAP S/4HANA in the Realize phase.
- C. Custom code is adjusted in System Conversion and developed in New Implementation of SAP S/4HANA in the Realize phase.
- D. Custom code is developed in System Conversion and adjusted in New Implementation of SAP S/4HANA in the Realize phase.
Answer: A,C
Explanation:
In System Conversion, custom code is adjusted to align with SAP S/4HANA requirements, while in New Implementation, custom code is developed anew. Additionally, data is converted in System Conversion, whereas in New Implementation, data is migrated from the legacy system.
NEW QUESTION # 22
Which estimation technique can you use in an Agile delivery approach to size the user stories during sprint planning?
- A. Relative effort estimate in Ideal Person Days that reflects the best estimate by the Project Team
- B. Detailed bottom-up effort estimate by the Product Owner that breaks up each story into short tasks
- C. Detailed top-down effort estimate by the Scrum Master in story points, based on the user story complexity
- D. Product Owner's relative effort estimate that will be needed to implement and test the user story
Answer: C
Explanation:
In Agile practices within SAP Activate, estimation is often conducted using "story points" to evaluate relative size and complexity. A top-down approach led by the Scrum Master ensures that all aspects of story complexity are considered, facilitating accurate, consensus-driven estimates.
NEW QUESTION # 23
When does the Scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?
- A. During the sprint review
- B. During the user acceptance test
- C. During the sprint retrospective
- D. During the daily Scrum meeting
Answer: A
Explanation:
* D is correct because the sprint review is the event where the Scrum team receives formal confirmation that the user stories are completed to the satisfaction of the product owner. The sprint review is a meeting where the Scrum team demonstrates the functionality that they have built and configured in the sprint, and the product owner provides feedback and acceptance. Verified References:
* : [What is a Sprint Review? | Scrum.org]
NEW QUESTION # 24
Which systems are part of the private cloud edition landscape? Note: There are 2 correct answers to this question.
- A. Evaluation
- B. Sandbox
- C. Starter
- D. Production
Answer: B,D
Explanation:
In the SAP S/4HANA private cloud edition, Sandbox and Production systems are part of the landscape, providing environments for testing and productive operations, respectively. These systems support the full lifecycle of deployment and ongoing maintenance.
NEW QUESTION # 25
Which of the following are levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package? Note: There are 2 correct answers to this question.
- A. Business Process Scenarios
- B. Scope Items
- C. Building Blocks
- D. Configuration Guides
Answer: B,C
Explanation:
In SAP Best Practices for SAP S/4HANA Solution Packages, Scope Items and Building Blocks represent structured components. Scope Items define functional aspects, while Building Blocks provide detailed configuration steps.
NEW QUESTION # 26
What is the correct phase order of an SAP Activate project?
- A. Prepare > Explore > Realize > Deploy > Run
- B. Prepare > Explore > Discover > Realize > Deploy
- C. Prepare > Discover > Explore > Realize > Deploy > Run
- D. Prepare > Explore > Realize > Deploy > Run
Answer: A
Explanation:
The correct phase order in the SAP Activate methodology for an SAP project is Prepare > Explore > Realize > Deploy > Run. This sequence represents the structured progression from project setup to solution deployment and operations.
NEW QUESTION # 27
Which functionality is available in Focused Build?
- A. Integration Monitoring
- B. Custom Code Management
- C. User Experience Monitoring
- D. Test Management
Answer: D
Explanation:
* B is correct because Focused Build provides a test management feature that supports the planning, execution, and reporting of test activities in SAP projects. It allows the creation and assignment of test cases, test packages, and test plans, as well as the tracking and monitoring of test results and defects.
Verified References:
* : Focused Build for SAP Solution Manager
NEW QUESTION # 28
What is the preferred option to migrate to SAP S/4HANA Cloud, private edition while keeping most of the original processes and adding new configuration?
- A. New Implementation
- B. System Conversion
- C. Mix and Match
- D. Shell Conversion
Answer: D
Explanation:
Shell Conversion allows for the migration of SAP S/4HANA Cloud, private edition, by bringing over most original processes while adding new configurations as needed, without a complete system overhaul.
NEW QUESTION # 29
What technique helps a Scrum team to prioritize a large, flat backlog?
- A. Fit-gap analysis
- B. Retrospective
- C. User story mapping
- D. Planning poker
Answer: C
Explanation:
* C is correct because user story mapping is a technique that helps a Scrum team to prioritize a large, flat backlog. User story mapping is a process of creating a visual representation of the user stories, grouped by themes, epics, and features, and ordered by value and dependency. It helps the team to understand the big picture and focus on the most important user stories for each sprint. Verified References:
* : User Story Mapping
NEW QUESTION # 30
Which of the following is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud, public edition" transition path?
- A. Setup and Enablement
- B. Fit-to-standard
- C. Simplification and Custom Code Impact Analysis
- D. Solution Validation and Delta Design
Answer: B
Explanation:
* B is correct because Fit-to-standard is part of the Explore phase in the "New Implementation of SAP S/4HANA Cloud, public edition" transition path. Fit-to-standard is a process where the customer validates the fit of their business processes to the standard SAP S/4HANA Cloud solution and identifies any gaps or extensions that need to be addressed. Fit-to-standard is performed using a series of workshops where the customer reviews the best practice processes and scenarios provided by SAP and compares them with their own requirements. Verified References:
* : SAP Activate Methodology for SAP S/4HANA Cloud, page 18
* : SAP Activate - Explore Phase: Use Fit-to-Standard to Confirm Business Process Fit and Identify Gaps in Your SAP S/4HANA Cloud Implementation
NEW QUESTION # 31
What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud, public edition?
- A. SAP Signavio Process Navigator
- B. SAP Cloud ALM
- C. SAP Roadmap Viewer
- D. SAP Transformation Navigator
Answer: B
Explanation:
SAP Cloud ALM is the tool designed for managing project tasks and Solution Documentation in SAP S/4HANA Cloud, public edition. It supports tracking project progress, documenting configurations, and ensuring that deliverables are on track.
NEW QUESTION # 32
You are defining the testing strategy for your project.
What would you include in a Scope of Integration test? Note: There are 2 correct answers to this question.
- A. The connectivity with other systems
- B. The connectivity between database and application servers
- C. The procedures for data migration
- D. The functionality of end-to-end business processes
Answer: A,D
Explanation:
The Integration Test focuses on validating the functionality of end-to-end business processes and ensuring connectivity with other systems. This test type confirms that integrated systems function together as expected.
NEW QUESTION # 33
Which of the following are levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package?Note: There are 2 correct answers to this question.
- A. Business Process Scenarios
- B. Scope Items
- C. Building Blocks
- D. Configuration Guides
Answer: B,C
Explanation:
* B is correct because Scope Items are one of the levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package. A Scope Item is a unit of business functionality that covers one or more business processes. A Scope Item has a description, a list of configuration steps, and a set of test cases.
* C is correct because Building Blocks are one of the levels in the structure of an SAP Best Practices for SAP S/4HANA Solution Package. A Building Block is a reusable component that contains configuration data, master data, or transactional data for a specific business area. A Building Block can be assigned to one or more Scope Items. Verified References:
* : [SAP Best Practices Explorer]
NEW QUESTION # 34
In which workshop do you validate SAP standard functionality and collect delta requirements?
- A. Design thinking
- B. Solution validation
- C. Fit-to-standard
- D. Fit-to-gap
Answer: C
Explanation:
* D is correct because Fit-to-standard is the workshop where you validate SAP standard functionality and collect delta requirements. Fit-to-standard is a process where the customer validates the fit of their
* business processes to the standard SAP solution and identifies any gaps or extensions that need to be addressed. Fit-to-standard is performed using a series of workshops where the customer reviews the best practice processes and scenarios provided by SAP and compares them with their own requirements.
Verified References:
* : [SAP Activate Methodology for SAP S/4HANA Cloud], page 18
* : [SAP Activate - Explore Phase: Use Fit-to-Standard to Confirm Business Process Fit and Identify Gaps in Your SAP S/4HANA Cloud Implementation]
NEW QUESTION # 35
Which systems are part of the private cloud edition landscape?Note. There are 2 correct answers to this question.
- A. Evaluation
- B. Sandbox
- C. Starter
- D. Production
Answer: B,D
Explanation:
* A is correct because Production is one of the systems that are part of the private cloud edition landscape.
The Production system is the system where the solution is deployed and operated for the end users. It contains the live data and processes of the customer's business.
* B is correct because Sandbox is one of the systems that are part of the private cloud edition landscape.
The Sandbox system is an optional system that can be used for testing, prototyping, or training purposes.
It is a copy of the Production system that can be refreshed on demand.
NEW QUESTION # 36
A customer with an existing SAP S/4HANA solution is exploring the best approach to move without changing their landscape into the cloud. Which is the most suitable option for the customer?
- A. Lift and Shift
- B. System Conversion
- C. Mix and Match
- D. Selective Data Transition
Answer: A
Explanation:
Lift and Shift is the preferred approach for customers aiming to move an existing SAP S/4HANA system to the cloud with minimal changes to their current landscape. This option focuses on infrastructure relocation rather than system transformation.
NEW QUESTION # 37
Which of the following best outlines the sequence of testing in the Realize phase?
- A. 1. Integration Test 2. User Acceptance Test 3. String test
- B. 1. Data Migration 2. String test 3. User Acceptance Test
- C. 1. String test 2. User Acceptance Test 3. Integration Test
- D. 1. String test 2. Integration Test 3. User Acceptance Test
Answer: D
Explanation:
* B is correct because String test > Integration Test > User Acceptance Test is the best outline of the sequence of testing in the Realize phase. The String test is performed first to verify the end-to-end processes across the system landscape. The Integration Test is performed next to verify the integration of the solution with other systems and interfaces. The User Acceptance Test is performed last to verify that the solution meets the customer's business requirements and expectations. Verified References:
* : SAP Activate Project Management Certification Guide, page 120
NEW QUESTION # 38
When deploying SAP S/4HANA Cloud, private edition using new implementation, which of the following is recommended to code custom developments? Note: There are 2 correct answers to this question.
- A. SAP Business Technology Platform
- B. SAP Best Practices
- C. SAP Support Portal
- D. SAP ABAP Workbench
Answer: A,D
Explanation:
For custom developments in SAP S/4HANA Cloud, private edition, SAP Business Technology Platform provides the environment for side-by-side extensibility, while SAP ABAP Workbench supports in-app custom development within the system.
NEW QUESTION # 39
Which of the following steps are part of the fit-to-standard process? Note: There are 2 correct answers to this question.
- A. Enable customers on standard business processes
- B. Document integration requirements
- C. Design to-be business process models
- D. Review Best Practices process flow
Answer: A,D
Explanation:
* B is correct because reviewing Best Practices process flow is one of the steps that are part of the fit-to-standard process. The Best Practices process flow is a diagram that shows the standard SAP functionality and configuration for a scope item. The project team reviews the Best Practices process flow with the customer to demonstrate how the solution supports their business processes, and to identify any gaps or extensions that need to be addressed.
* D is correct because enabling customers on standard business processes is one of the steps that are part of the fit-to-standard process. The project team enables customers on standard business processes by providing them with access to a starter system, where they can explore and test the predefined configuration and sample data for each scope item. The project team also provides customers with training materials and guidance on how to use the solution. Verified References:
* : [SAP Activate Methodology for SAP S/4HANA Cloud], page 18
* : [SAP Activate - Explore Phase: Use Fit-to-Standard to Confirm Business Process Fit and Identify Gaps in Your SAP S/4HANA Cloud Implementation]
NEW QUESTION # 40
A customer with an existing SAP S/4HANA solution is exploring the best approach to move their landscape into the cloud.Which is the most suitable option for the customer?
- A. Lift and Shift
- B. System Conversion
- C. Mix and Match
- D. Selective Data Transition
Answer: A
Explanation:
* D is correct because Lift and Shift is the most suitable option for a customer who wants to move their existing SAP S/4HANA solution into the cloud. It involves moving the entire system landscape from one environment to another without changing the system configuration or data. Verified References:
* : SAP Activate Project Management Certification Guide, page 128
NEW QUESTION # 41
Which collaboration features are available in the SAP Community? Note: There are 2 correct answers to this question.
- A. Comment on Key Deliverables
- B. Update Key Deliverable wikis
- C. Ask questions
- D. Follow community
Answer: C,D
Explanation:
In the SAP Community, users can ask questions to seek assistance from other members and follow topics or communities to stay informed about relevant discussions. These features foster collaborative learning and engagement.
NEW QUESTION # 42
......
SAP C-ACT-2403 Exam Syllabus Topics:
| Topic | Details |
|---|---|
| Topic 1 |
|
| Topic 2 |
|
| Topic 3 |
|
| Topic 4 |
|
| Topic 5 |
|
| Topic 6 |
|
| Topic 7 |
|
SAP Certified Associate Fundamentals-C-ACT-2403 Exam-Practice-Dumps: https://www.pass4surequiz.com/C-ACT-2403-exam-quiz.html
Use Real C-ACT-2403 Dumps - SAP Correct Answers: https://drive.google.com/open?id=19kvnQfn4YQAlyqzSxyi8QNCxBkKirPrB