SAP C_TS422_1909 Exam Syllabus Topics:

TopicDetails
Topic 1
  • Select and apply planning strategies, use the planning table
  • Advanced Planning in SAP S/4HANA
Topic 2
  • Outline both motivation and background of SAP S/4HANA
  • Determine BOM item category
  • Describe order status management and set user statuses
Topic 3
  • Explain line load planning and confirmation
  • outline the capabilities of embedded analytics
Topic 4
  • Identify repetitive manufacturing specific master data
  • Apply material staging and confirmation
Topic 5
  • Differentiate consumption-based planning vs. MRP, outline new trends in production planning
  • Configure availability check for components
Topic 6
  • Describe the SAP HANA database concept and new user experience with SAP Fiori
  • Identify and explain production relevant master data
Topic 7
  • Introduction to SAP S/4HANA Supply Chain Planning
  • Material Requirements Planning in SAP S/4HANA

 

NEW QUESTION 29
How can Production Planning and Detailed Scheduling (PP/DS) enhance the standard planning functionality?
Please choose the correct answer.
Response:

  • A. By providing multilevel material requirements planning
  • B. By providing cross-plant planning and deployment
  • C. By providing future demands from demand figures in the past
  • D. By providing replenishment proposals with exact times

Answer: D

 

NEW QUESTION 30
What are some of the SAP Fiori user types?
There are 3 correct answers to this question.
Response:

  • A. Expert
  • B. Occasional
  • C. Business partner
  • D. Employee
  • E. Developer

Answer: A,B,E

 

NEW QUESTION 31
Which of the following processes lead to an entry in the MRP planning file? Note: There are 3 correct answers to this question.

  • A. Change of the storage bin
  • B. Creation of a purchasing contract
  • C. Change of the material's procurement type
  • D. Creation of a sales order
  • E. Creation of dependent requirements

Answer: C,D,E

 

NEW QUESTION 32
Before a user can add multiple production versions in a material master, what information should be collected?
There are 3 correct answers to this question.
Response:

  • A. Validity dates
  • B. Task list group number
  • C. Work center hierarchy
  • D. BOM status
  • E. Lot sizes

Answer: A,D,E

 

NEW QUESTION 33
Which of the following is a valid sequence of the main activities in product on order processing?

  • A. Creation, scheduling, release, variance calculation, confirmation
  • B. Creation, release, scheduling, material withdrawal, confirmation
  • C. Creation, staging, release, material withdrawal, confirmation
  • D. Creation, scheduling, release, material withdrawal, confirmation

Answer: D

 

NEW QUESTION 34
Which of the following apply to MRP Live?
There are 2 correct answers to this question.
Response:

  • A. The sequence of planning materials is calculated across plants.
  • B. The definition of the planning scope is more flexible.
  • C. Planned orders need to be converted to purchase requisitions for externally procured materials.
  • D. The BAdIs for classical MRP also apply to MRP Live.

Answer: A,B

 

NEW QUESTION 35
Which master data object governs the relationship between supply source and demand source in the Kanban process?

  • A. Rate routing
  • B. Control cycle
  • C. Replenishment strategy
  • D. Production supply area

Answer: B

 

NEW QUESTION 36
At the end of the MRP run you receive the exception message "Reschedule In Operation". What caused the message to be generated?
Please choose the correct answer.
Response:

  • A. The requirement no longer exists
  • B. The requirements date occurs before that of a firmed planned receipt
  • C. The requirements date occurs that of a firmed planned receipt
  • D. A firmed planned receipt cannot be rescheduled

Answer: B

 

NEW QUESTION 37
Which functional capabilities does the Detailed Scheduling Board have?
There are 2 correct answers to this question.
Response:

  • A. Change planned order quantities
  • B. Undo for drag & Drop planning activities
  • C. Enter time-ticket confirmation for production orders
  • D. Change sales order quantities

Answer: A,B

 

NEW QUESTION 38
In which of the following master data objects can you define the production order default storage location for a material component?
There are 2 correct answers to this question.
Response:

  • A. Work center, in the production supply area
  • B. Routing, in the component allocation
  • C. Material master of the finished product
  • D. BOM, in the item for the material

Answer: A,D

 

NEW QUESTION 39
What does the bill of material usage (BOM usage) control at the BOM item level?
Response:

  • A. Maximum allowed low-level code
  • B. Allowed material type
  • C. Default unit of measure
  • D. Default values for the item status

Answer: B

 

NEW QUESTION 40
Which of the following are capabilities of multidimensional reporting in SAP S/4HANA embedded analytics?
There are 3 correct answers to this question.
Response:

  • A. Scheduling
  • B. Sort
  • C. Filters
  • D. Forecast
  • E. Drilldown

Answer: B,C,E

 

NEW QUESTION 41
Which SAP solutions can be used for forecast ng in Supply Chain Planning? Note: There are 2 correct answers to this question.

  • A. Material Requirements Planning (MRP)
  • B. Supply Chain Management (SCM)
  • C. Capacity Requirements Planning (CRP)
  • D. Integrated Business Planning (IBP)

Answer: B,D

 

NEW QUESTION 42
You want to set up a make-to-order planning scenario for a finished material. Some components from the bill of materials (BOM) should be procured per sales order, other components should be procured for various requirements. Fore casting is NOT possible. Which settings do you make to achieve this?

  • A. Planning strategy 50 (Planning without final assembly) and the corresponding individual Collective Indicator.
  • B. Planning strategy 20 (Make-to-Order) and the corresponding Mixed MRP indicator
  • C. Planning strategy 20 (Make-to-Order) and the corresponding individual Collective indicator
  • D. Planning strategy 50 (Planning without final assembly) and the corresponding Mixed MRP indicator

Answer: A

 

NEW QUESTION 43
Your production planners must execute planning only for specific resources. How can you achieve this in Advanced Planning (PP"/OS)?

  • A. Use a planning group.
  • B. Use a resource group.
  • C. Use a heuristic.
  • D. Use a propagation range.

Answer: C

 

NEW QUESTION 44
You are using heuristic SAP_ERP_001. Which of the following criteria are included in the automatic source determination logic when a planned order is created?
Please choose the correct answer.
Response:

  • A. Quota arrangement
  • B. Vendor rating
  • C. Component availability
  • D. Delivery date
  • E. Costs

Answer: A

 