Get Prepared for Your C_TS412_2021 Exam With Actual 112 Questions [Q17-Q35]

Share

Get Prepared for Your C_TS412_2021 Exam With Actual 112 Questions

Valid C_TS412_2021 Test Answers Full-length Practice Certification Exams


SAP C_TS412_2021 certification exam is designed for professionals who are seeking to validate their skills and knowledge in SAP S/4HANA Project Systems. SAP Certified Application Associate - SAP S/4HANA Project Systems certification is ideal for those who are involved in project management, including project managers, team members, and consultants.


SAP C-TS412-2021 certification exam is designed to test the skills and knowledge of professionals who work with SAP S/4HANA Project Systems. SAP Certified Application Associate - SAP S/4HANA Project Systems certification demonstrates that the candidate has the necessary skills to manage and execute projects using SAP S/4HANA Project Systems.

 

NEW QUESTION # 17
Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question

  • A. The factory calendar in the work center used for the internal processing activity
  • B. The relationships between activity elements
  • C. An activated Scheduling indicator in the control key of the internal processing activity
  • D. The unit (for example, hour, day) of the field Normal Duration field of the activity
  • E. Whether the work for the internal activity is greater than its duration

Answer: A,B,C

Explanation:
The scheduling of internal processing activities is influenced by several factors, such as the control key, the activity elements, and the factory calendar. The control key is a parameter that defines the basic properties of an activity, such as whether it is internally or externally processed, whether it requires confirmation or not, and whether it is relevant for scheduling or not. The scheduling indicator in the control key determines whether an activity is included in scheduling or not. The activity elements are subordinate units of an activity that represent partial tasks or work packages. The relationships between activity elements define the logical sequence and dependencies of the partial tasks. The factory calendar is a parameter that defines the working days and holidays for a work center. The factory calendar affects the duration and dates of an activity that uses the work center. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 18
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct answers to this question

  • A. Planned revenue requires a sales order assigned to a WBS element
  • B. Planned revenue can be transferred from a sales quotation
  • C. Actual revenue is posted via a billing plan assigned to a WBS element
  • D. Actual revenue is posted via a billing document created from a sales order

Answer: A,D

Explanation:
Planned revenue and actual revenue are two types of revenue for WBS elements in SAP Project System. Planned revenue requires a sales order assigned to a WBS element, which means that the sales order item contains the data for revenue planning, such as quantity, price, and billing plan. Actual revenue is posted via a billing document created from a sales order, which means that the billing document records the delivery of goods or services to a customer and requests payment for them. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 19
The various work packages in the project are described as individual______________. Choose the correct answer.

  • A. Project definitions
  • B. WBS elements
  • C. Activities
  • D. Tasks

Answer: B


NEW QUESTION # 20
To which object can you assign a factory calendar?

  • A. Material component
  • B. Network header
  • C. Milestone
  • D. Relationship

Answer: B


NEW QUESTION # 21
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation., and have entered the quotation ...
What is the typical sequence for the following business transactions and document.

  • A. Vendor selection - purchase order handing- purchase order monitoring- Benefic Check- Acceptance of performed services.
  • B. Vendor selection - purchase order handing - invoice receipt - purchase order monitoring -Good receipt.
  • C. Benefic check - Acceptance of performed service- vendor selection - purchase order handing- purchase order monitoring-Good receipt - invoce ..
  • D. Vendor selection- Purchase order handing-purchase order monitoring-Good receipt- Invoice receipt.

Answer: D

Explanation:
"The typical sequence for the following business transactions and documents is: Vendor selection - Purchase order handling - Purchase order monitoring - Goods receipt - Invoice receipt." Reference: 1


NEW QUESTION # 22
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?

  • A. Only capacity requirements
  • B. Backward
  • C. Current date
  • D. Forward

Answer: B


NEW QUESTION # 23
What is the reason for assigning billing plans in customer projects?

  • A. Billing plans are used for revenue planning.
  • B. Billing plans are copied automatically to the sales order item.
  • C. Billing plans enable the billing process to be carried out.
  • D. Billing plans are prerequisites for quotation creation.

Answer: C


NEW QUESTION # 24
A customer needs to analyze the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct answers to this question

  • A. Structure information system reports
  • B. Cost element reports
  • C. Resource reports
  • D. Hierarchical reports

Answer: A,C


NEW QUESTION # 25
Which planning method can prevent further rescheduling of activities?

  • A. Capacity levelling
  • B. Partial confirmation of activities
  • C. Capacity requirements activation
  • D. Workforce planning

Answer: C


NEW QUESTION # 26
You want use a template to create a new project with network in the Project Builder (CJ20N). Which template can you use in Project builder?
Note : there are 3 correct answer for this question.

  • A. Project definition
  • B. Project version.
  • C. Project milestone
  • D. Standard Project definition
  • E. Standard network

Answer: A,D,E

Explanation:
A template is a predefined structure that can be used to create a new project with network in the Project Builder (CJ20N). You can use different types of templates depending on your requirements and preferences. Some of these templates are:
Standard network: This is a template that contains predefined activities, relationships, milestones, and components for a network. You can use a standard network to create a new network with similar structure and content.
Standard Project definition: This is a template that contains predefined WBS elements, networks, activities, relationships, milestones, and components for a project. You can use a standard project definition to create a new project with similar structure and content.
Project definition: This is an existing project that can be used as a template for creating a new project with network. You can use a project definition to copy the entire structure and content of an existing project or only selected parts of it. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/1ad4b65334e6b54ce10000000a174cb4.html?locale=en-US&state=PRODUCTION&version=2020.002


NEW QUESTION # 27
Project Structures
Which the following statement regarding networks are correct?.
Note : there are 3 correct answers for this question.

  • A. You can assign the same work center to more than one activity on the same network.
  • B. Capacity requirements of a network activity are reduced when the activity is confirmed.
  • C. If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
  • D. During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
  • E. You can assign more than one activity element to a network activity.

Answer: A,B,E

Explanation:
"You can assign more than one activity element to a network activity." According to SAP Help Portal, "Capacity requirements of a network activity are reduced when the activity is confirmed." According to SAP Press4, "You can assign the same work center to more than one activity on the same network." Reference: 4


NEW QUESTION # 28
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question

  • A. In the project profile
  • B. In the project definition of a standard WBS
  • C. In the operative WBS element
  • D. In the project type
  • E. In the project version

Answer: A,B,C


NEW QUESTION # 29
A component is assigned to a network activity. What are the prerequisites to generate project stock reservations? Note: There are 3 correct answers to this question

  • A. The network is assigned to a sales order item
  • B. A procurement indicator must be assigned to the activity
  • C. The Project Stock indicator is set in the project definition (non-valuated or valuated)
  • D. The material master of the component must permit project stock management
  • E. The network activity is assigned to a WBS element

Answer: C,D,E


NEW QUESTION # 30
What could be a reason to use expert mode in the valuation method for results analysis?

  • A. Usage of different line ID
  • B. Assignments of different accounts for postings to financial accounting
  • C. Billing WBS elements belonging to different company codes
  • D. Valuation in different currencies

Answer: C


NEW QUESTION # 31
You want to set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing. Which influencing field do you use?

  • A. Network profile
  • B. Network type
  • C. Project profile
  • D. Data entry profile

Answer: D


NEW QUESTION # 32
Cost and Budget
What function are available for period end-closing in the project System?

  • A. Progress analysis
  • B. Confirmation
  • C. Milestone trend analysis
  • D. Result analysis
  • E. Settl ement

Answer: A,C,D


NEW QUESTION # 33
You are using networks and external activities in your project The purchase requisition has been created. What is the sequence for the following business transactions and documents?

  • A. Vendor selection -> Purchase order handling -> Invoice receipt- Purchase order monitoring -> Goods receipt
  • B. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval
  • C. . Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt -> invoice receipt
  • D. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt

Answer: D


NEW QUESTION # 34
Where do you control whether a project stock is managed as valuated or non-valuated project stock?

  • A. In the WBS element
  • B. In the project definition
  • C. In the material master
  • D. In the network activity

Answer: B


NEW QUESTION # 35
......