NEW QUESTION 31
An architect is designing a vSphere environment for a customer and learns that the customer has:
A single vSphere cluster
Two storage arrays with different RAID capabilities
Which two design decisions should the architect make to maximize data availability and data performance for this customer? (Choose two.)

  • A. Use a minimum of three storage arrays.
  • B. Use multiple datastores for heartbeat.
  • C. Use Storage DRS.
  • D. Use VM to host DRS rules.
  • E. Use VMDK anti-affinity rules.

Answer: B,C

 

NEW QUESTION 32
Application owners require support of a Microsoft Windows Server Failover Cluster (WSFC).
Their current environment consists of the following components:
vSphere 7.0 and vSAN 7.0
External array supporting NFS 3.0/4.1, Server Message Block (SMB) 2.1
10 GbE storage connectivity for all devices
The solution architect is tasked with coming up with a solution to meet this requirement while utilizing their existing investments.
Which two recommendations could the architect make? (Choose two.)

  • A. Use the SMB 2.1 protocol for sharing disks
  • B. Use vSAN native support for WSFC
  • C. Run WSFC on vSAN iSCSI Target Service
  • D. Use raw device mapping (RDM)
  • E. Use NFS 4.1 shares for quorum and shared disk

Answer: A,B

 

NEW QUESTION 33
Following a recent acquisition, an architect needs to merge IT assets into its current data center. The combined vSphere environment will need to run the newly acquired company's virtual machines.
Network integration work has already been completed and the current environment has capacity to host all virtual machines. The Operations team needs to identify which virtual machines belong to the acquired company and report on their usage.
How should the architect merge the company's assets and virtual machines?

  • A. Lift and shift the acquired assets into the data center
  • B. Leave the newly acquired company's assets in its current place
  • C. Migrate and apply vSphere tags to the acquired company's virtual machines
  • D. Migrate the acquired company's virtual machines into the existing vSphere environment

Answer: C

 

NEW QUESTION 34
An architect is tasked with designing a new VMware software-defined data center (SDDC) solution for an online retail customer who has a primary and secondary data center as well as 10 distribution hubs.
The customer has provided the following business requirements to help inform the design:
The solution must support the running of up to 1,000 concurrent virtual machines across the primary and secondary data center.
The solution must support the running of up to 20 concurrent virtual machines in each distribution hub.
The solution must support the separation of management and lines-of-business application virtual machines.
All management components (including directory services, backup, automation, operations and logging) must be deployed to the primary data center.
All virtual infrastructure components must have redundancy of N+1.
All sites are connected to each other using a wide area network that has multiple diversely routed links.
The solution should support a monthly uptime target of 99.9%.
The recovery time objective (RTO) for the solution must be four hours.
The recovery point objective (RPO) for the solution must be 24 hours.
Given the information from the customer, which assumption should the architect include in the design?

  • A. Each distribution hub should be configured with a backup device.
  • B. The wide area network has sufficient bandwidth to support centralized management.
  • C. All business application virtual machines can be deployed into a single cluster within the primary data center.
  • D. Each cluster will have a minimum of four hosts.

Answer: B

 

NEW QUESTION 35
An architect is preparing a design for a company planning digital transformation. During the requirements gathering workshop, the following requirements (REQ) and constraints (CON) are identified:
REQ01 The platform must host different types of workloads including applications that must be compliant with internal security standard.
REQ02 The infrastructure must initially run 100 virtual machines.
REQ03 Ten of the virtual machines must be compliant with internal security standard.
REQ04 The internal security standard specifies logical network separation for in-scope applications.
CON01 The customer has already purchased the licenses as part of another project.
CON02 The customer has five physical servers that must be reused.
Additionally, based on resource requirements, four physical servers will be enough to run all workloads. Which recommendation should the architect make to meet requirements while minimizing project costs?

  • A. Purchase additional servers and plan separate, isolated clusters for workloads that must be compliant with internal security
  • B. Use Network I/O Control to ensure the internal security zone has higher share value
  • C. Use a single cluster and configure DRS anti-affinity rules to ensure internal security compliant virtual machines cannot migrate between ESXi hosts.
  • D. Use a single cluster and ensure that different security zones are separated at least with dedicated VLANs and firewall

Answer: D

 

NEW QUESTION 36
A customer defines a requirement to minimize the vMotion migration time during a maintenance period. The servers being used are equipped with eight 1 GbE network adapters.
Per the defined logical network configuration, there are two network adapters each used for:
Management traffic
vMotion traffic
iSCSI traffic
Virtual machine traffic
Which design decision should the architect make to meet the customer requirement?

  • A. Configure a dedicated TCP/IP stack for vMotion traffic.
  • B. Combine vMotion and Management traffic to make use of four adapters.
  • C. Use Network I/O Control to define a reservation for vMotion traffic.
  • D. Implement Multi-NIC vMotion by adding additional vMotion VMkernels.

Answer: D

Explanation:
https://kb.vmware.com/s/article/2007467
https://communities.vmware.com/t5/VMware-vSphere-Discussions/vmotion-load-balanced-across-multiple-uplinks-on-distributed/td-p/491336
https://www.virtuallyboring.com/multi-nic-vmotion/
We maintain the 2 x 1 GbE network adapters for vMotion and then configure multiple VMkernel interfaces using the same NIC and network. Each time you add a VMkernel adapter and enable it for vMotion, you create a new stream. With more streams, there is greater bandwidth utilization.

 

NEW QUESTION 37
Refer to the exhibit.

During a requirements gathering workshop, the customer shares the following about their existing ESXi host virtual networking infrastructure:
The customer confirms that:
Each ESXi host has approximately 200 virtual machines.
They want to maximize the number of concurrent virtual machine migrations.
When placing a host in maintenance mode, it takes a long time to evacuate the virtual machines.
Which two recommendations should the architect make in order to help the customer overcome their challenge? (Choose two.)

  • A. Configure the network to use MTU for the VMotion VMKernel to 1,600 bytes
  • B. Use the 3 pNICs and bundle them in a link aggregation group (LAG) configuration
  • C. Configure the network to use MTU for the VMotion VMKernel to 9,000 bytes
  • D. Create an additional standard switch with pNIC3 to use for vMotion
  • E. Use 10 GbE NICs instead of 1 GbE

Answer: D,E

 

NEW QUESTION 38
Refer to the exhibit.
During a requirements gathering workshop, a customer shares the following diagram regarding their availability service-level agreements (SLAs):

The customer states that there is no application level availability for legacy applications.
Which recommendation could the architect make to meet the customer's high availability requirements for the legacy applications virtual machines?

  • A. Enable vSphere HA and add a VM Override with VM Restart Priority set to Disabled
  • B. Enable vSphere HA and add a VM Override with VM Restart Priority set to Lowest
  • C. Achieve application availability with snapshots
  • D. Enable Fault Tolerance

Answer: A

Explanation:
Explanation/Reference:

 

NEW QUESTION 39
An architect is tasked with designing a greenfield VMware software-defined data center (SDDC) solution that will be used to deliver a private cloud service for a customer.
During the initial meeting with the service owner and business sponsor, the customer has provided the following information to help inform the design:
The solution must support the concurrent running of 1,000 virtual machines The production environment must be delivered across two geographically dispersed data centers All virtual machines must be capable of running in either data center.
The two data centers are currently connected to each other through a single but diversely routed, high bandwidth and low latency link.
The link between the two data centers is capable of supporting a round-trip time (RTT) of 150 ms The existing server hardware standard document states that all virtual infrastructure hosts must be deployed using vSAN ReadyNodes The service owner has stated that it is critical to ensure the availability target of 99.9% All virtual machine backups must be completed using the existing backup service The recovery time objective (RTO) for the service is five minutes The recovery point objective (RPO) of the service is four hours Which two elements represent risks to the successful delivery of this solution? (Choose two.)

  • A. The clusters will have a minimum redundancy of N+1
    "The service owner has said that is important to ensure that neither the availability target of 99.5% nor the resource capacity is affected when the operations team completes maintenance activities" We assume N+1 is sufficient. They may require a higher level of redundancy.
  • B. The use of vSAN ReadyNodes
  • C. The backup service has sufficient capacity for the new requirements
    "All virtual machine backups must be completed using the existing backup service." The existing backup service may not have capacity or compatabiltiy for the new SDDC
  • D. The use of only two data centers
  • E. The use of the existing backup service
  • F. The RTT on the link between the two data centers
  • G. The network connectivity between data center sites

Answer: E,G

 

NEW QUESTION 40
During a requirements gathering workshop, the customer provides the following requirement (REQ) and constraints (CON):
REQ01: The customer is looking for a way to limit database virtual machine (VM) placement to save on CPU licensing costs.
CON01: There is a single cluster with no budget to scale.
CON02: All virtual machines must run on the consolidated cluster.
Which two design decisions should the architect make to meet the customer requirement? (Choose two.)

  • A. The solution must use vSphere VM and host DRS groups
  • B. The solution must use a vRealize Orchestrator workflow for VM placement
  • C. The solution must use vSphere DRS in manual mode
  • D. The solution must use VM-VM anti-affinity rules
  • E. The solution must use VM-Host affinity rules

Answer: A,E

 

NEW QUESTION 41
Which two statements are true about gathering functional business and application requirements? (Choose two.)

  • A. It builds stakeholder consensus
  • B. It leverages a single set of Question:s for all stakeholders
  • C. It might require multiple rounds of stakeholder interviews
  • D. It focuses on functional requirements with C-level stakeholders
  • E. It is a non-iterative process

Answer: C,D

 

NEW QUESTION 42
An architect is tasked with designing a greenfield VMware software-defined data center (SDDC) solution that will be used to deliver a private cloud service for a customer.
During the initial meeting with the service owner and business sponsor, the customer has provided the following information to help inform the design:
The solution must initially support the concurrent running of 300 production and 600 development virtual machines.
The production environment should be delivered across two geographically dispersed data centers. The development environment must be vSphere-based but does not have to be deployed on-premises.
The two data centers are connected to each other through multiple diversely routed, high bandwidth and low latency links.
The customer's server hardware standard document states that all virtual infrastructure hosts must be based on blade architecture only.
The service owner has said that is important to ensure that neither the availability target of 99.5% nor the resource capacity is affected when the operations team completes maintenance activities, such as the monthly software patching and ad-hoc hardware break/fix.
All virtual machine backups must be completed using the existing backup service. The recovery time objective (RTO) for the service is four hours.
The recovery point objective (RPO) of the service is 24 hours.
Given the information from the customer, which two would be classified as assumptions within the design? (Choose two.)

  • A. The backup service has sufficient capacity for the new requirements
  • B. The backup service will store data in a secure facility
  • C. The clusters will have a minimum redundancy of N+1
  • D. All virtual machines will be deployed with the same resource profile for production and development
  • E. The customer will update their hardware standard to support rack mount servers

Answer: B,E

 

NEW QUESTION 43
An organization's data scientists are executing a plan to use machine learning (ML). They must have access to graphical processing unit (GPU) capabilities to execute their computational models when needed. The solutions architect needs to design a solution to ensure that GPUs can be shared by multiple virtual machines.
Which two solutions should the architect recommend to meet these requirements? (Choose two.)

  • A. vSphere Bitfusion
  • B. vSGA
  • C. AMD MxGPU
  • D. vSphere DirectPath I/O
  • E. NVIDIA vGPU

Answer: B,E

 

NEW QUESTION 44
An architect is designing a new backup solution for a vSphere platform that has been recently upgraded to vSphere 7.
The architect wants the backup solution to perform the following:
Full virtual machine image backup and restore
Incremental virtual machine image backup and restore
File level backup and restore within both Windows and Linux virtual machines LAN-free backup Which functional requirement should the architect include in the design of the new backup solution?

  • A. The backup solution must leverage the VMware Consolidated Backup (VCB) framework.
  • B. The backup solution must leverage VMware vSphere Storage APIs - Data Protection.
  • C. The backup solution must leverage virtual machine snapshots.
  • D. The backup solution must leverage VMware vStorage APIs for Data Protection (VADP).

Answer: B

Explanation:
https://kb.vmware.com/s/article/1021175

 

NEW QUESTION 45
An architect will be taking over control of a former Linux server fleet and repurposing the hardware into a new vSphere cluster. The current environment is already connected to the network but the hosts do not have any local disks. Since the fleet hardware is uniform, the architect can use a single ESXi image. All hosts within the cluster have the same CPU and memory capacity.
Which ESXi deployment method should the architect use?

  • A. Stateless cached vSphere Auto Deploy
  • B. Manual install of each ESXi host with an image from USB
  • C. Stateless vSphere Auto Deploy
  • D. Stateful vSphere Auto Deploy

Answer: A

Explanation:
Explanation/Reference: https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.esxi.install.doc/GUID-0813B4BE-
485D-4129-902B-49AA42EBF54E.html

 

NEW QUESTION 46
A VMware Service Provider is tasked with delivering a solution for continuous availability for a subset of Tier 1 virtual machines (VMs) and vApps running in their vSAN environment. The VMs make up a mission-critical application and there can be no data loss in the event of an outage at their primary data center. In the event of a regional outage, they have established a 10-minute recovery point objective (RPO). Failover/failback to the third site must be automated.
They have the following in place:
Two local data centers (primary and secondary) connected with 100 Gb dedicated fiber
2ms round-trip time (RTT) latency between the sites A third data center located on another power grid
70ms latency between the primary and secondary data centers
Matching storage arrays at all locations
Which two solutions could be used to meet the requirements? (Choose two.)

  • A. vSAN Metro Cluster
  • B. Snapshots
  • C. vStorage APIs for Array Integration (VAAI)
  • D. Site Recovery Manager
  • E. vSphere Data Protection

Answer: A,B

 

NEW QUESTION 47
An architect is designing a new vSphere platform for a customer to meet the following requirements:
The platform must be deployed into five physically separate sites.
The sites are spread across multiple regions.
Some sites require more than one vCenter Server.
The platform must provide an administrator with the ability to access virtual infrastructure components across all sites from a single management tool instance.
Which single sign-on (SSO) design recommendation will meet these requirements?

  • A. Use an SSO domain per region
  • B. Use an SSO domain across all vCenter Server instances
  • C. Use an SSO domain per site
  • D. Use an SSO domain per vCenter Server instance

Answer: D

 

NEW QUESTION 48
An architect is planning the physical server configuration for a vSAN-based infrastructure.
Which operations mode should a RAID controller support to minimize potential server downtime during physical disk failures?

  • A. RAID controller with RAID 6 mode
  • B. RAID controller with RAID 10 mode
  • C. RAID controller with RAID 5 mode
  • D. RAID controller with Passthru mode

Answer: D

 

NEW QUESTION 49
An architect is preparing a design for a company planning digital transformation. During the requirements gathering workshop, the following requirements (REQ) and constraints (CON) are identified:
REQ01 The platform must host different types of workloads including applications that must be compliant with internal security standard.
REQ02 The infrastructure must initially run 100 virtual machines.
REQ03 Ten of the virtual machines must be compliant with internal security standard.
REQ04 The internal security standard specifies logical network separation for in-scope applications.
CON01 The customer has already purchased the licenses as part of another project.
CON02 The customer has five physical servers that must be reused.
Additionally, based on resource requirements, four physical servers will be enough to run all workloads. Which recommendation should the architect make to meet requirements while minimizing project costs?

  • A. Use a single cluster and ensure that different security zones are separated at least with dedicated VLANs and firewall
  • B. Purchase additional servers and plan separate, isolated clusters for workloads that must be compliant with internal security
  • C. Use Network I/O Control to ensure the internal security zone has higher share value
  • D. Use a single cluster and configure DRS anti-affinity rules to ensure internal security compliant virtual machines cannot migrate between ESXi hosts.

Answer: D

 

NEW QUESTION 50
An architect is tasked with expanding an existing VMware software-defined data center (SDDC) solution so that it can be used to deliver a virtual desktop infrastructure (VDI) service off-shore development activities.
The production environment is currently delivered across two geographically dispersed data centers. The two data centers are currently connected to each other through multiple diversely routed, high bandwidth and low latency links. The current operations management components are deployed to a dedicated management cluster that is configured with N+1 redundancy. The current VMware software-defined data center (SDDC) has a monthly availability target of 99.5%, which includes all management components.
The customer requires that the new solution scale to support the concurrent running of 500 persistent virtual desktops. The virtual desktops must not share the same virtual infrastructure as existing virtual machines, but can be managed using the same VMware operations management components. Any new VDI service management components must be installed into the management cluster. There is no requirement to back up the virtual desktops because all relevant user data is stored centrally. The VDI service is providing business critical services and must have an availability target of 99.9%.
Given the information from the customer, which two assumptions would the architect include in the design? (Choose two.)

  • A. The existing management cluster has enough available capacity to host any VDI service management component
  • B. The existing operations monitoring tools have sufficient capacity to monitor the new VDI services
  • C. The VDI service has a higher service-level agreement (SLA) than the operations management SLA
  • D. The existing virtual infrastructure has sufficient capacity to host the new VDI workloads
  • E. The management cluster has N+1 redundancy

Answer: B,D

 

NEW QUESTION 51
An architect is tasked with reviewing the design of a VMware software-defined data center (SDDC) for a software development company. The platform is used to developing applications and services. It is important that the customer be able to accurately benchmark performance of developed applications.
The platform has recently commissioned new hosts to update the development cluster.
The development cluster host configuration is:
* 4 ESXi hosts with 2 sockets × 16 cores
* 512 GB RAM divided evenly between sockets
* There is no resource contention
The benchmarking cluster host configuration is:
* 8 ESXi hosts with 2 sockets × 8 cores
* 256 GB RAM divided evenly between sockets
* There is no resource contention
The customer is developing an application that includes a database virtual machine. The application developer states that the database virtual machine performs as required only when allocated 8 vCPUs 256 GB RAM. The database virtual machine performance meets the required levels when run from the development cluster.
Performance benchmarking for the database virtual machine yields highly variable results when run from the benchmarking cluster. The application cannot be released without reliable performance benchmarking data.
What is a possible reason for the difference in performance test results between the development and benchmarking clusters?

  • A. The database tier breaches a single NUMA node boundary for the benchmarking cluster
  • B. The development cluster has more available RAM per host
  • C. The development cluster can support a lower %Ready time per vCPU
  • D. The database tier breaches a single NUMA node boundary for the development cluster

Answer: C

 

NEW QUESTION 52
An architect is designing a new vSphere environment to meet the following requirements:
The environment must support 5,000 virtual machines.
The environment will be built initially using 350 hosts.
Which vCenter Server appliance deployment size should the architect specify for the design?

  • A. Tiny
  • B. Small
  • C. Medium
  • D. Large

Answer: C

Explanation:
For more details:
- Tiny environment (up to 10 hosts or 100 virtual machines)
- Small environment (up to 100 hosts or 1,000 virtual machines)
- Medium environment (up to 400 hosts or 4,000 virtual machine)
- Large environment (up to 1,000 hosts or 10,000 virtual machines)
- X-Large environment (up to 2,500 hosts or 45,000 virtual machines)
https://docs.vmware.com/en/VMware-vSphere/7.0/com.vmware.vcenter.install.doc/GUID-88571D8A-46E1-464D-A349-4DC43DCAF320.html

 

NEW QUESTION 53
......

Verified 3V0-21.21 dumps Q&As - 100% Pass from Pass4SureQuiz: https://www.pass4surequiz.com/3V0-21.21-exam-quiz.html

Pass 3V0-21.21 Exam in First Attempt Guaranteed 2022 Dumps: https://drive.google.com/open?id=1vvY41Sr4xKRRD0YxKXE7OksMSleFxKQ_